TransportationTop story
Crews slid the northbound Abernethy Bridge about eight feet over the weekend
The slide moved the bridge slowly to widen it
- 8 feet
- the northbound side moved, about
- 4 inches
- every 15 minutes during the slide
- 16 feet
- of roadway the project adds in the middle
Sources: Lake Oswego Review, KATU
If you cross the Willamette on I-205, you felt this one. The Oregon Department of Transportation finished sliding the northbound side of the Abernethy Bridge on Fri., Nov. 20 and Sat., Nov. 21. Crews moved it onto new earthquake-reinforced concrete piers four inches every 15 minutes, working around the clock.
- Northbound I-205 was closed from late Friday night until early Monday morning
- Ramps closed: OR 43, 10th Street and Stafford Road
- Next: southbound side slides "another weekend later this year"
- ODOT construction is expected to finish in 2027
Many residents didn't feel properly informed about the closure, and considered the detour to the Oregon City Arch Bridge poorly managed. KATU says the goal is to add 16 feet of roadway in the middle, with the southbound lanes sliding the other way. We suggest signing up for alerts at i205corridor.org.
The northbound slide is done and the southbound slide is next
- Nov. 20Northbound I-205 closes at 10 p.m. between OR 99E and OR 43.
- Nov. 21Crews finish the northbound slide begun Friday.
- Nov. 23Northbound I-205 reopens at 5 a.m.
- Late 2026Crews slide the southbound side of the bridge.
- 2027ODOT construction is expected to be complete.
Sources: Lake Oswego Review, KATU