The Abernethy Bridge just slid almost 8 feet sideways, and the other half is next
The northbound section weighs about 9,060 tons
- 1,030 feet
- long, the northbound section crews moved
- 9,060 tons
- is about what that section weighs
- 8 feet
- is roughly how far it slid sideways
- 16 feet
- of added space once both slides finish
Source: News Radio 1190 KEX
If you cross I-205 between Oregon City and West Linn, the bridge under your tires just moved. Over the weekend, crews slid a 1,030-foot northbound section almost 8 feet onto newly widened, earthquake-resilient piers. KGW reports the section weighed over 9,000 tons.
Crews lifted the section about two inches with hydraulic jacks, then pushed it about four inches every 15 minutes. ODOT closed northbound lanes from 10 p.m. Fri., Nov. 20 and shut the OR 43, 10th Street and Stafford Road on-ramps.
- Southbound slide: still to come, with no date set
- Holiday timing: crews don't expect it on a major holiday weekend
- Gap in the middle: 16 feet once both slides finish
- Bridge construction: expected to finish in 2027
The northbound slide is done and the southbound half comes next
- Nov. 20Northbound I-205 lanes close at 10 p.m. across the Abernethy Bridge.
- Nov. 21Crews slide the 1,030-foot northbound section almost 8 feet in about six hours.
- Nov. 23Northbound lanes reopen ahead of schedule after inspections and restriping.
- Dec. 2026The southbound half will move about 8 feet the other way; no date set.
- 2027Bridge construction is expected to finish sometime in 2027.
Sources: KGW, News Radio 1190 KEX, KATU, KOIN.com
Northbound lanes reopened early Monday, ahead of schedule. We suggest checking ODOT's current highway conditions before the southbound closure.